What is an Action Submittal?

Study for the CSI Construction Documents Technology (CDT) Exam. Learn with flashcards and multiple choice questions, each question has hints and detailed explanations. Get ready to ace your exam!

Multiple Choice

What is an Action Submittal?

Explanation:
Action submittals are submittals that require a response from the design professional—usually a formal review and approval—before the work proceeds. They are the means by which the contractor demonstrates that proposed materials, equipment, or methods conform to the contract documents, and the architect/engineer must review and either approve, approve with comments, or reject them. Examples commonly cited are Product Data, Shop Drawings, and Samples because each provides information that the design team must evaluate against the design intent and specifications. Informational submittals, by contrast, do not require a formal decision; they are provided for information or record-keeping rather than to obtain a directive from the architect/engineer. A project schedule or a final warranty document typically falls into that informational category rather than requiring ongoing design action. Thus, the definition that emphasizes submittals requiring a responsive action by the A/E (review and approval) with those specific examples is the best fit for what an Action Submittal is.

Action submittals are submittals that require a response from the design professional—usually a formal review and approval—before the work proceeds. They are the means by which the contractor demonstrates that proposed materials, equipment, or methods conform to the contract documents, and the architect/engineer must review and either approve, approve with comments, or reject them. Examples commonly cited are Product Data, Shop Drawings, and Samples because each provides information that the design team must evaluate against the design intent and specifications.

Informational submittals, by contrast, do not require a formal decision; they are provided for information or record-keeping rather than to obtain a directive from the architect/engineer. A project schedule or a final warranty document typically falls into that informational category rather than requiring ongoing design action. Thus, the definition that emphasizes submittals requiring a responsive action by the A/E (review and approval) with those specific examples is the best fit for what an Action Submittal is.

Subscribe

Get the latest from Passetra

You can unsubscribe at any time. Read our privacy policy